Archer completes first phase of septic-to-sewer conversion project

Archer has finished the first of three phases in a project to replace the city’s septic systems with a sewer connection, with city leaders announcing phase one was completed on time and within its $6.5 million budget. The initial phase installed eight miles of main transfer pipe linking Archer to Newberry, and residents who connect to the new system within a specified window will not face hookup costs. Two more phases remain, including work on state-controlled road crossings and construction of a collection system inside Archer, with the full project expected to take about two more years.